Adding Additional Dollars to a Step and Lane in a Salary Schedule

Note:  Additional dollars can also be entered when building the Salary Schedule - Percents table for the package.

  1. From the Negotiations screen, select the Maintenance menu and then Salary Schedules.

  2. At the Salary Schedules screen, enter the ID of the package for which to enter the additional dollars in the Package ID field, or click the down-arrow button to select the correct one.

  3. The Salary Schedule - Amounts table for the specified package will display.

  4. Click the Edit tab; or if desired, double-click on the cell (step and lane) on the table instead to view the information specific to the particular cell and then continue with Step 7.

  5. Enter the number of the desired step to enter the additional dollars in the Step field, or click the down-arrow button to select the correct one.

  6. Enter the number of the desired lane to enter the additional dollars in the Lane field, or click the down-arrow button to select the correct one.

  7. The information for the selected step and lane appears.

  8. Enter the additional dollar amount to be added to the salary for the specified cell in the Additional Dollars field.  The amount can be up to 14 digits long (including the decimal point and comma(s) if applicable) and will be rounded to 2 decimal places by the system if capable.

  9. Click the Save button.

  10. Repeat Steps 5-9 to enter additional dollars for other cells (steps and lanes).

  11. When done, click the Salary Schedules tab to view the tables.